Hot pour crack sealing

Overview

The work covered by this section of the specification consists of furnishing all plant, labor, equipment and materials necessary to perform all operations in connection with the reshaping, cleaning and filling of construction and random cracks in bituminous concrete pavements and vegetation removal and sterilization of cracks where necessary.

  • Federal Specification SS-S-164 or 1401b hot-poured joint sealer.
  • SS-C-192g Portland cement, type 1 or 2.
  • Bituminous treated hemp or jute roving, or reclaimed neoprene material ground to maximum size of 1/4″ to 1 1/4″.

Technical Specifications

RANDOM CRACK SEALING BITUMINOUS CONCRETE PAVEMENTS

1. Scope
The work covered by this section of the specification consists of furnishing all plant, labor, equipment and materials necessary to perform all operations in connection with the reshaping, cleaning and filling of construction and random cracks in bituminous concrete pavements and vegetation removal and sterilization of cracks where necessary.

2. Materials

  • Federal Specification SS-S-164 or 1401b hot-poured joint sealer.
  • SS-C-192g Portland cement, type 1 or 2.
  • Bituminous treated hemp or jute roving, or reclaimed neoprene material ground to maximum size of 1/4″ to 1 1/4″.

3. Equipment
Equipment used in the performance of the work required by this section of the specification shall be subject to the approval of the engineer and maintained in a satisfactory working condition at all times.

  • Equipment for reshaping cracks shall be vertical spindle or rotary-type cutter or router.
  • Air Compressor: Air compressors shall be portable and capable of furnishing not less than 100 cubic feet of air per minute at not less than 90 pounds per square inch pressure at the nozzle. The compressor shall be equipped with traps that will maintain the compressed air free of oil and water.
  • Manually operated, gas powered air-broom or self-propelled sweeper designed especially for use in cleaning highway and airfield pavements shall be used to remove debris, dirt and dust from routed cracks.
  • Hand tools shall consist of brooms, shovels, metal bars with chisel-shaped ends and any other tools which may be satisfactorily used to accomplish this work.
  • Melting Kettle: The unit used to melt the joint sealing compound shall be double-boiler, indirect-fired type. The space between the inner and outer shells shall be filled with a suitable heat transfer oil or substitute having a flash point of not less than 600°F. The kettle shall be equipped with a satisfactory means of agitating the joint sealer at all times. This may be accomplished by continuous stirring with mechanically operated paddles and/or by continuous circulating gear pump attached to the heating unit. The kettle must be equipped with thermostatic control calibrated between 200°F and 500°F.
  • Hand-pouring pots must be equipped with mobile carriage and have a flow control valve which allows all cracks to be filled to refusal so as to eliminate all voids or entrapped air, and not leave unnecessary surplus crack sealer on pavement surfaces.

4. Preparation

  • Cleaning – All cracks shall be thoroughly cleaned to remove all dirt, moisture, foreign material and loose edges from crack wall. Compressed air and/or routing may be utilized.
  • Debris Removal – All old material and other debris removed from the cracks shall be removed from pavement surface immediately by means of power sweepers, hand brooms or air brooms.
  • Vegetation – When cracks show evidence of vegetation, it shall be removed and, if necessary, sterilized by use of propane torch unit, eliminating all vegetation, dirt, moisture and seeds.
  • All cracks of sufficient depth and 3/4″ or over in width shall first be pre-filled with bituminous treated hemp or jute roving, or reclaimed neoprene material ground to maximum size of 1/4″ to within 1″ of top of pavement before applying prepared joint sealer.
  • When necessary to allow vehicle traffic to pass over crack sealer prior to curing, dry Portland cement shall be dusted over cracks to eliminate pick-up.
  • General – No crack sealing material shall be applied in wet cracks or sheer frost, snow or ice is present, nor when ambient temperature is below 320F.

5. Preparation of Sealer
Joint sealing material shall be heated and applied at temperature specified by the manufacturer and approved by the engineer.

6. Installation of Sealer
All cracks shall be sealed as specified herein, and the sealer shall be well bonded to the pavement. Unless otherwise directed, the cracks shall be completely filled flush with the pavement and not less than 1/4″ below surface, without formation of voids or entrapped air.

7. Workmanship
All workmanship shall be of the highest quality and excess or spilled sealer shall be removed from the pavement by approved methods and discarded. Any workmanship determined to be below the high standards of the particular craft involved wil not be accepted and will be corrected and/or replaced as required by the engineer in charge.

8. Performance
It is the intentions of the Public Agency not to award a contract for this work under this or any other proposal if the bidder cannot furnish satisfactory evidence that he has the ability and experience to perform this class of work and that he has sufficient capital and equipment to enable him to prosecute the work successfully and to complete it within the time named in the contract; and that the Public Agency reserves the right to reject this or any other proposal or to award the contract as is deemed to be the best interest of said Public Agency.

The contractor must submit with his bid proposal a list of six (6) jobs which he has successfully completed, giving the name and the address of these projects so they can be investigated prior to the award of the contract.

9. Sampling and Testing:
Joint sealer will be tested for conformance with Federal Specification SS-S-164 or 1401 b. Joint material sample shall be submitted for approval prior to start of the work. Manufacturing certificates that joint sealer meets Federal Specification listed above will be accepted by the engineer, unless otherwise stated in specification proposals.

Imagine installing a product as friendly to install as an asphalt based beautifier with a lot of the same strengths as a coal tar based sealer.   Action-Pave LP Base Sealer
In this installment, Copeland provided USTA Eastern a step-by-step view of a recent court repair and resurfacing project at Katonah Memorial Park in Katonah, NY. Please check out the PDF of the full article!

Our company has been doing business with Copeland Coatings for over twenty-five years. They complete all of our projects on time and on budget. We have never had a quality control problem with their work. They are professionals in their field. I give Copeland Coatings my highest recommendation.

Tom Vandish Bast Hatfield

Copeland Coating has been resurfacing tennis, basketball, and volleyball courts at Camp Scatico for more than 25 summers. They’ve completed every project on time and on budget. What more can you ask for?

Scatico Camp

We have worked with Copland Coating for well over twenty years. There work is outstanding and they stand by the what they do. John and Steve have always been responsive to our needs. Copland is a 1st rate organization.

Dave Tager Indian Head Camp

I would like it to be known that Copeland Coating is a wonderful company to do business with. I am the Head Tennis Coach at Bard College and have had dealings with Copeland in the person of Steve Puzio over these past 20 years. We have used Copeland as our “got to” company for all our court needs. Our six courts have been resurfaced twice. Steve was involved personally from start to completion both times. He came first to advise and determine our needs, followed by a quote.

He made himself accessible always and we eagerly walked the job after the courts dried to insure our total satisfaction. Copeland allowed us to commit to an acceptable time frame for the job. We were always treated respectfully and fairly. Their many years of experience proved invaluable as their advice was always “spot on”. I feel that they are the best in the business. I am sure you will agree.

Bard College

Camp Starlight has been dealing with Copeland Coating for many years. We have used Copeland for all of our sports courts including tennis, basketball, and gymnasium surfaces. The work has always been of a very high quality and they have always been very responsive to any of our requests. Even in times of inclement weather Copeland has always worked overtime to get the job completed on schedule. I would have no hesitation in recommending Copeland Coating to any camp.

David Miller Starlight Camp

Island Lake has employed Copeland Coating for over 25 years. We have found them to be professional and a quality provider of court surfacing. They are consistently on time and perform as expected. We wouldn’t look anywhere else for this service.

Matt Stoltz Island Lake Camp

Copeland coating goes the extra coating when it comes to great customer service. For 12 years it’s been a straight set victory for our member tennis courts!

Sportsplex

I have had the privilege of working closely with Copeland Coating Company over the years in the development of our tennis facilities at Saratoga Springs High School and Middle School.

I have always found them to be easy to work with during and after the completion of their work. They were always available to advise when needed. They are the best at what they do and I highly recommend them!

Rich Johns Tennis

Island Lake has employed Copeland Coating for over 25 years.
We have found them to be professional and a quality provider of court
surfacing. They are consistently on time and perform as expected. We wouldn’t
look anywhere else for this service.

Matt Stoltz Island Lake Camp

Just a quick note to thank you once again for the terrific job you did with our courts this spring. Over the past 15 years we have enjoyed the relationship with you and Copeland Coating, and have come to trust your judgement and expertise. You have always communicated timely with us, finished your work ahead of schedule, and the quality of work is impeccable.

We look forward to many more years together – see you at Tri-State.

Mark Newfield Owner/Director, Iroquois Springs